The upgrades are complete. Check your Monday email for more details. Don't forget to update your timezone setting (https://test.kuali.org/confluence/users/editmypreferences.action). This will ensure you see correct times in the calendar and the time of any page updates is accurate.
Release Roadmap Endorsed by Functional Council
The KS Functional Council endorsed the proposed overall release schedule (see last week's news) at their Sep 18th meeting. Highlights from the meeting:
- Focusing on grade collection and program audit early will test performance.
- Early Learning Plan work will provide new functionality for students.
- UMCP and UBC plan to begin data conversion and configuration after release R2a and to go live with some components after R2b.
- Learning Plan components in R2 will present the biggest challenge for the design team.
- Amount of Scheduling included in R2a to be reviewed so only bare minimum included.
- R1, R2 Roadmap Recap (RRRR)
Release 1 - Learning Unit Inventory: Learning units (courses, programs, projects, experiential learning, learning objectives) will be created and serve as foundation for relationships between learners and learning units in Enrollment.
Release 2a - LU Instance Environment: Creation of instances of learning units (LUI) to which learners are enrolled. LUI is the foundation for creating historical records and registering into current offerings.
Release 2b - LUI Learning Results to Learners (back-end): Creation of historic relationships between learners, LUIs and learning results (grades, degrees, etc). Foundation for support of prerequisites, benchmark/annual evaluations, registration calendaring, etc. Evaluation of the learning completed by students (Program Audit and Evaluation) and core aspects of Learning Plan will begin.
Release 2c - Register Learners in current LUI offerings (registration): Registration of learners into specific learning instances including management of seat pools, waitlist management and integration with the Learning Plan and Program Audit.
Tuesday Leadership Meetings
The Steering Committee and Team Leads will begin to meet separately on alternating weeks, i.e. this week the Team Leads met, next week the larger Steering Committee will meet.
This week the Team Leads discussed consistency, efficiency and coordination among teams as we move toward development of R1. Discussion focused on inter-team communications with current teams composition and leadership and accountability remaining unchanged. 'Agile Scrum' labels were replaced with 'Point People' and 'Owner' labels. The discussion continues.
Functional and service implementation specs will start to be available in Nov. Additional bundles of specs will be delivered periodically until Mar 2009.
Use Case Team Planning Workshop
The Use Case/UX teams are planning a Release 2 workshop for around the end of Oct or beginning of Nov.
Team Highlights
Full Status Reports at https://test.kuali.org/confluence/x/TwBvBQ, and https://test.kuali.org/confluence/x/WwFcBQ
Last week
- UC: Finished Create Program and Create LUT, Modify and Retire Program close, Authorize Person in progress, 4 melanges remain.
- UX: Presented sample UI component spec and wireframe to App Design team.
- SVCS: Reviewed Learning Unit, Contact & Communication services, releasing next week. Explored CLU and LUI relations using course examples, and worked on interplay between Rules and LU.
- RICE: Gary built new version of Rice, setup vmware for Oracle on a Mac & met with UCSD & IU in San Diego
- Transactions: PoC2 build in progress
- Rules: Repository service and API done; Rules Mgmt Service (RMS) is close; UI for RMS in progress; Fact Finder Svc prelim design done
- ADT Haiku: On the Equinox, Pondering a first Melange, Many leaves to rake
- ADT: Apply Functional Spec to 'Create and Process a Course Proposal'
- UC: Finish remaining Melanges, finalize direction of Authorize Person, finalize R2 workshop plans
- UX: Work out structure and methodology for sharing component spec and wireframe development within UX group.
- SVCS: Work on person, authorization, authentication & AZ group services. More work on defining the interplay between LU and Rules, and further exploration of CLU and LUI relations for using course & program examples, start completing Service Implementation Specs
- Transactions: Build PoC2 and explore options for access to linux cluster for test lab
Berkeley News
KS Team Open House
Thanks to James (w/ help from Sara and Yu-Tin), RSVPs are rolling in for the KS Team Open House on Oct 2nd, 2-4pm. We will attempt to stream the event live via http://www.ustream.tv/channel/kuali-student for anyone who can't be here in person.
Mingling on Campus, Fun and Educational
Last week Sara & James attended the L&S Undergraduate Division Fall Reception. They met new faces: Physics Professor Bob Jacobsen, Programmer Russ Connacher, USAF Lt. Col. Brian Stone of the Dept of Aerospace Studies and the new Dean of Undergraduate Advising Tyler Stovall among others. They learned new things: the ROTC program, the soon-to-be-released undergraduate advising system ISIS, and the trials of articulation and advising. And ate good food. Thanks to James for bringing this and other campus events to the team's attention. I encourage you to take advantage of these informal information gathering and relationship building opportunities.
News from Around the University of California System
The following highlights were gleaned from the University of California Information Technology Leadership Council quarterly reports, see: http://www.ucop.edu/irc/itlc/.
Kuali Financial System @ UC
UC Irvine has developed an initial Kuali Project Team to assess and plan for replacing their current financial systems w/ Kuali Financial System (KFS). UC Davis has functional and technical staff working on KFS modules to be released Dec 2008 and is working on their implementation plan (http://accounting.ucdavis.edu/projects/UCDKuali/). UC Irvine, UC Davis, UC Santa Barbara, UC Office of the President (UCOP) are working on a UC specific Chart of Accounts configuration for KFS.
Kuali RICE @ UC
UC Irvine is evaluating RICE as replacement forExpresso Java Application Development Framework. Irvine has identified three RICE proof-of-concept applications using eDocLite. UC San Diego is also investing in RICE. Gary summarized his visit to a UCSD hosted RICE meeting in an 9/19 email.
Kuali Coeus / Kuali Research Administration @ UC
UCLA has a new student records system that achieved 'Code Complete' status in June 2008. They moved their enrollment and registration systems to Java. Testing and integration with other campus systems will be completed in 0809 academic year.
Portal Work Everywhere
UC Irvine developing a student portal w/ uPortal 3.0 with plans to go live in May 2009. See http://wiki.vcsa.uci.edu/bin/view/Portal or contact Kevin Ansel
Email Outsourcing
UC Davis is starting to outsource student email to Google, see http://technews.ucdavis.edu/news2.cfm?id=1671.
Calendar
October
2
- Functional Council Meeting
- Berkeley KS Team Open House
6,7
- UC Enrollment Services Technology Conference Oakland
6,7,8,9
- Infrastructure Integration Workshop UMaryland
-18
Use Case starts on R2
20
- KS Board Review of Release Roadmap
End of Oct
Possible Use Case Release 2 Workshop